-52-

REPAIRS, RESTORATION AND CODE COMPLIANCE - FIVE YEAR DEVELOPMENT PROGRAM

45-HIRSHHORN MUSEUM & SCULPTURE GARDEN-45

[[8 column table]]

SUBCATEGORIES | FY '88 | FY '89 | FY '90 | FY '91 | FY '92 | FY '93 | FY '94 and Beyond

1. GENERAL REPAIRS & IMPROVEMENTS
Parapet & Wall Ventilation | 0 | 50 | 450 | 0 | 0 | 0 | 0
Court Sill (3rd & 4th Floor) | 0 | 0 | 200 | 0 | 0 | 0 | 0
Pressure Grouting/Sandblasting-Sculpture Garden | 0 | 0 | 5 | 0 | 0 | 0 | 0

2. FACADE, ROOF & TERRACE REPAIRS
Court Glass & Gaskets | 0 | 235 | 0 | 0 | 0 | 0 | 0
Plaza Resurfacing and Landscaping | 300* | 1,900 | 0 | 0 | 0 | 500 | 0
Roof Inspection Survey | 0 | 10 | 0 | 0 | 0 | 0 | 0

3. FIRE DETECTION & SUPPRESSION
Sprinkler System/Ground Floor | 80 | 0 | 0 | 0 | 0 | 0 | 0

4. ACCESS, SAFETY & SECURITY IMPROVEMENTS 
Minor Safety/Security Projects | 110 | 0 | 0 | 0 | 0 | 0 | 0

5. UTILITY SYSTEM REPAIRS & IMPROVEMENTS
Miscellaneous HVAC Projects | 0 | 100** | 375 | 675 | 25 | 0 | 120
Interior Lighting Modifications | 0 | 0 | 0 | 0 | 25 | 0 | 0
Relocation & Replacement of Condensate Pumps | 0 | 0 | 200 | 0 | 0 | 0 | 0

6. ADVANCED PLANNING & INSPECTION
No Projects Identified | [[underlined]]0 | 0 | 0 | 0 | 0 | 0 | 0[[/underlined]]

TOTALS: | 490 | 2,295 | 1,230 | 675 | 50 | 500 | 120

* Funding in FY'90 required for landscaping is pending the completion of A/E study which is to be completed by the 1st quarter FY'88. FY'93 funding is subject to revision pending same study and implementation of Space Use Master Plan.
** FY '89 Funds to address 'Backlog of Essential Maintenance & Repair' projects where deferral to Master Plan implementation is not possible.

Page : 13   Date: July 7, 1987, revised October 23, 1987