after SITE test, OSTA --> OPF (can't be installed until after RMS is in orbiter) in OPF: copper path test; electrical load test (trying to run with fuel cell 3) OIT planned for early July (no RCN from CH5 yet) STS-2 test team exists (lead by Bob Reed?) @ KSC. scheduling mtgs MWF @ 9:30. --> plan trip for 4/27 to see (1) OSTA SITE test (2) RMS unpacking (3) orbiter (back in OPF) RCS (SST session) RCS mals during entry. Im mm 301-303, ~same as on-orbit. mm 304/305 different. (Forward RCS not commanded in 304). • PASS leak detection : FU/OX QTY differ by 12% (this is reset after each detection) (FDF) • p 8.7 of entry PCL : (1) The IF statement before reconfiguration of lte PRESS A, B is confusing (2) some checks require "reading fine print" and performing actions ... some don't. --> FDF forms in SST/SMS?