5. 


*6. The ALS has been completed to a full 3000' system. Commissioning of facility pending satisfactory flight check.

7. Delivery of inner marker scheduled for October 1967. Commissioning scheduled for November 1967. 

8. F&E continuous power project engineering will start Spring of 1968. Project completion, due to Washington equipment delivery, will be during 1968 construction season.

9. Continuous power project for owner facilities not yet programmed. No estimated completion date available.

Milwaukee, Wisconsin

Runway 1
200 feet wide; 9,916 feet long; CPA Runway 1

Estimated commissioning December 1967

*1. Capture Effect Glide Slope required to meet Category II standards. Equipment shipped during October 1967. Necessary grading has been completed. Glide slope shut down September 22, 1967 and relocation of building has been completed. Antenna tower construction in progress. Estimated completion date December 31, 1967.

2. Touchdown zone and centerline lights (L-850) are being installed and programmed for completion December 1967. 

3. Rollout RVR transmissometer scheduled for installation December 1967. The computer and associated equipment to commission this transmissometer will not be delivered until April 1968. 

4. Inner marker equipment delivered.

5. F&E continuous power project scheduled for completion February 1968.

6. Continuous power project for owner facilities is under FAAP grant. Schedule for completion is March 1, 1968.