6/4/81
BFS Testing - STS-2
Have we covered all STS-2 Δ's @ right level?
Don Dellehunt
Frank Cauclion
Frank Hattabaugh - SMS review, test cases, verif[[?]] test matrices
Charlie Wang  Closed-loop verif[[?]]
Gary Raines
Charlie Price - JSC BFS tech mgr
Ted Humphrey/BFS Subsys Mgr
Jim Greenly, Tony Cook SDL

H-04 all CRs to 5/18
+ all STS-1 discrepancies fixed 4 waivers fixed

Level 7
TRD's - ascent SOD80-0300
STS-2 D/O SOD80-0301
orbit SOD80-0302

Charlie Whang overall
Pat Richardson (FSL) reqts 1/F,
Harvey Fyall (SAIL) schedule

Level 1-4 done by S/W developer (module by module; often desk)
5 build tape testing
level 6 open loop captured sim testing; integrated S/W modules
development level SMS's
level 7 SAIL, FSL, D/L - integrates modules; some performance

RI [[strikethrough]]pich[[/strikethrough]] pitch on method/sched for Level 6,7
RI counterparts to come to JSC in 2-3 wks . . .
((one-on-one renews

*See Story, Tony about SAIL & FSL 1/F's TED HUMPHREY = Ed Shevecs STS-2
*Assemble CB list of CR's, waivers, patches