7

24 Nov 81

TITLE___________________
Project No.___
Book No.___ 

From Page No.__

IUS Handover - Lounge
Stan Blackmer Bosticks guy, S/W
Wayne Owens Launch Site Support Mgr ([[strikethrough]] CS [[/strikethrough]]) [[strikethrough]] CB [[/strikethrough]] (CP-DPO)
* Joe Fitzsimmons Test Team Leader (CS-MVD-1) - cargo C/O details
John VanHooser Vehicle ops guy (VE-PEO)
JJ Cornwell CH 6370
Bob Cohen WT-3 JSC OMRSD guy.
USAF; Western Union; TRW; NASA; Integration contractor space com

[8th GOWG held Oct 21-22, 1981
[Test team a subset of GOWG - "real" working level supposedly.
Met Nov 17, 1981

IUS/TDRS Mech mate done in VPF

"P/L Mission-unique S/W verification" - very mushy
CAS - Computer Augmented Site - do SM MSN-unique S/W verification somewhere other than SAIL.
Flt 5 going this way w/ SSUS; IUS simpler.
* OMRSD regmts not defined
Test regmts; facility constraints; GFE/GSE support; how to test & what to test
-> Need [[crossout]] OMRED [[/crossout]] OMI's by Feb/Mar '82 for 12/82 launch

ISSUES - STS-6 Flow 10/15/81

1. REQMTS def for S/W verf, cargo I/F test, VPF ETE test

2. reqmts & orb sys-up reqmts for pad cargo I/F/MCCH/ETE test

3. Dry CDDT probable if 1st flt of OV-099

4. TDRS battery conditioning 1 wk prior launch requires PBD re-opening @ T-7 days, final closeout T-72 hrs.
Late charging preserves B/U deploy opportunities
Trickle - charge through drag - on cables

To Page No._____

Witnessed & Understood by me, __________________
Date _________________
Invented by __________________
Recorded by __________________
Date ____________________

Transcription Notes:
---------- Reopened for Editing 2023-03-29 10:33:48 ---------- Reopened for Editing 2023-03-29 12:25:35 ---------- Reopened for Editing 2023-03-29 14:01:20 ---------- Reopened for Editing 2023-03-29 16:18:19 ---------- Reopened for Editing 2023-03-30 08:09:51