Project No.__
TITLE 1/11/82  Book No.__ 41 
From Page No._
Vehicle Status
  
Powered up 0200
V1061 preps in work
OSS-1 installed; DFRC access GSE fit checks in work
2 hyd leaks over weekend - swayed T & RSB PDU (sys3 vice Sys 2 line)
MMU #1 retest cmplt
IECM lifting and functionals done
PRSD line work complete (braising etc) done for cryo tank install n 
APU oil flush to be done vertical so no MMIT sitting on seal.
A6 PDRS TV panel to be pulled & spare put in (B145 call) - to fix STS-2 problem with 1 camera apparently running too fast & running out of film.
PBD seal repair cmplt; final closeout today.
IPR's
164 - Fwd PCA RPC T/S found proced/confy error (no pwr on RJDF bus A) Successfully retested this am.
151 - No MSBLS range lock. Believe they found a GSE problem.
168 - GPC 1 self fail. Procedural.
169 - SSME 1 GO2 check valve leak; seal replaced
126 - check valve - retested OK
167 - MPS solenoid valve leaking
170 - DEV 2 failed to go to RUN - [[crossed-out]] l [[/crossed-out]] insufficient time given to DEV 1 load

GAS going in today. I/F test probably tomorrow morning.

REM markings? - Should have whiskers on guides & tips of pins painted black. Make sure we've got em by S0031 time.
- Lee Harrison - called her to check it out

To Page No.___
Witnessed & Understood by me,_____
Date_____
Invented by_____
Recorded by_____
Date_____

Transcription Notes:
---------- Reopened for Editing 2023-03-30 09:45:08 ---------- Reopened for Editing 2023-03-30 11:08:07