Book No._____ 
77
From Page No._

5/13
V1010 (hyd) ~12 hours down
V1153 cmplt
H2O service/compression cks I/W
1037 preps I/W
Boron strut replaced
*CPES still I/W. Match drill didn't match 
V1009 I/W
*Actuator - hope hyd's done by 2nd tonight, then actr,
Ck rev removed & boroscoped. Repl I/W
*Humed separator plugged. 13-15#/hr flow w/ slurper in loop ~60^#/hr without it. Ted S. says expects wave for jet, John Rector JSC(4171)
H20 TK 1 valve - found short in a wire @ clamp
DACS concerns want in; cal today.
Hoping locker fit cks 3rd Fri.
*TCDT T-O no earlier than 5/29