2. [[underlined]] Preceding Period [[/underlined]]

Graphics package was approved by NASM, bids to be invited.

Carpet package, including colors, was finalized and forwarded to Federal Supply for procurement.

Orders for the Auditorium and Spacearium seating were placed with FSS for procurement thru a schedule contract.

Elevator equipment was delivered to the site and installation has begun.  Masonry partitions and dry-wall partitions have commenced and are proceeding very well.

3. [[underlined]] Plans for Current Period [[/underlined]]

Prepare graphics contract for bid.  Issue solicitations for carpeting.  Begin ordering furniture thru FSS.  Close out contract on Watermain Relocation, Structural Steel, and Metal Deck.  Issue change orders affecting the auditorium.  Revise specifications for auditorium projection screen.  Continue mechanical, electrical, window wall, skylight, etc. as planned.

4. [[underlined]] Potential Problems [[/underlined]]

The auditorium changes requested by NASM after the February 2, 1974, cutoff date may have an adverse effect on the project since the numerous changes requested will severely tax the contractors involved.