-105-

will focus on roof replacement, and $1,000,000 is included in the FY 1981 budget request for this purpose. About $1,000,000 is included in the FY 1982 request, and substantial resources will be required to sustain progress on this project throughout the planning period.

During FY 1980, detailed measured drawings and specifications for the replacement of the Renwick Gallery facade were completed. The first major construction phase will begin in FY 1981 with funds appropriated in FY 1980 ($600,000) and requested in FY 1981 ($1,000,000). At this time, cost estimates comparing precast concrete and natural stone are being updated for final evaluation before construction starts. It is estimated that a minimum of $3,000,000 will be required to complete this project between FY 1982 and FY 1986.

The facade and terrace of the Air and Space Musuem require a variety of repairs and improvements in order to eliminate water leaks and intrusions that have developed since the building was completed in 1975; the terrace also should be resurfaced with a more durable material. An amount of $650,000 is included in the FY 1981 budget request to begin construction, and additional funding of about $1,7000,000 is expected to be requested in future year budgets to continue this project.

Additional projects scheduled during this planning period include completion of the History and Technology terrace repair; caulking and pointing the facades of the Fine Arts and Portrait Galleries, History and Technology and Natural History buildings; resurfacing the plaza of the Hirshorn Museum; repairing windows at the Natural History building and Renwick Gallery; and double-glazing windows at several museums to improve energy efficiency. A total requirement of approximately $17,230,000 is anticipated for this planning period.

[[underlined]]Fire Detection and Suppression Systems.[[\underlined]] The Institution is continuing to develop and implement plans for upgrading fire protection systems in all buildings in order to provied a level of saftey consistent with today's standards and technology. Work in this category includes such items as the installation of heat and smoke detection systems, sprinkler and chemical supression systems, and fire doors and walls. Improved systems are installed as exhibitions are changed, and fire retardant materials are used wherever possible.

Comprehensive fire protection master plans have been completed for both the Natural History building and the History and Technology building. These plans outline programs for the installation of upgraded sprinkler systems, new detection systems, fire pumps, generators and control panels, and architechtural modifications to create more efficient fire zones. Steady progress has been made in implementing the plan for the Natural History building. The installation of a sprinkler system in the building's east wing will begin in FY 1981, in addition to other improvements. The master plan for the History and Technology building was completed duriong FY 1980, and the first major construction phase will start in FY 1981. A total requirement of