REPAIRS, RESTORATION AND CODE COMPLIANCE - FIVE YEAR DEVELOPMENT PROGRAM
32-SMITHSONIAN INSTITUTION BUILDING-32

[[8 column table]]
SUBCATEGORIES | FY '88 | FY '89 | FY '90 | FY '91 | FY '92 | FY '93 | FY '94 and Beyond

1. GENERAL REPAIRS & IMPROVEMENTS
Tunnel Repair & Waterproofing | 0 | 100 | 0 | 0 | 0 | 0 | 0

2. FACADE ROOF & REPAIRS
Facade Restoration (masonry) | 50 | 50 | 50 | 50 | 0 | 0 | 0 
Window Replacement | 1,250 | 750 | 620 | 160 | 0 | 0 | 0
Roof Inspection & Survey | 0 | 30 | 0 | 0 | 0 | 0 | 0
Repointing of SI Building Facade | 0 | 0 | 250 | 0 | 0 | 0 | 0 

3. FIRE DETECTION & SUPPRESSION
Smoke Detection/Sprinklers/Fire Zones | 250 | 250 | 250 | 0 | 0 | 0 | 0

4. ACCESS, SAFETY & SECURITY IMPROVEMENTS
No Projects Identified | 0 | 0 | 0 | 0 | 0 | 0 | 0

5. UTILITY SYSTEM REPAIRS & IMPROVEMENTS
Utility Systems Study/Energy Audit/Implementation | 0 | 70 | 0 | 0 | 0 | 0 | 0
Miscellaneous HVAC Projects | 0 | 55 | 0 | 0 | 0 | 0 | 0
Redesign & Replace SI Steam Station | 0 | 0 | 0 | 0 | 300 | 0 | 0
Reutilize Exhaust Air | 0 | 0 | 0 | 0 | 300 | 0 | 0 
Miscellaneous Mechanical Improvements | 0 | 85 | 0 | 0 | 0 | 0 | 0

6. ADVANCED PLANNING & INSPECTION
Structural Inspection , Pre-planning Study & Implementation | 100* | 100 | 500 | 0 | 0 | 0 | 0 
Basement Space Use Master Plan Study | 0 | 65 | 50 | 400 |0 | 0 | 0 

TOTALS: | 1,650 | 1,555 | 1,720 | 610 | 600 | 0 | 0

*FY '88 funds for study with subsequent funding for design and implementation in the outyears.

Page : 4 Date: July 7, 1987, revised October 23, 1987