-24-

[[three column table]]

CRITERIA | BWI | DULLES

9. COST ESTIMATES 		
One-Time Costs (1995-$) 		
Phase I | 16,310 | 11,858
Phase II | 5,881 | 5,881
Phase III | 11,469 | 11,469
Total | 33,660 | 29,208
		
Annual Operating Costs (1995-$)		
Phase I | 9,822 | 9,822
Phase II | 13,502 | 13,502
Phase III | 16,885 | 16,885
		
10. FLEXIBILITY 

Restricting Factors | narrow parcel, wetlands, height controls. topography, smaller size | narrow parcel, wetlands
Future acres for Smithsonian Use | 46 | 54
		
11. PHASING
 		
Phase I | √ | √
Phase II & III | smaller size area may restrict construction staging | construction may interrupt US 50 access

[[/three column table]]