approach:
1. SMS needed for STS-1/RMS support
2. if this plan is adopted, then stopped....  what have we gained/lost?
- ~150K spent productively (needed anyway - flexibility, retention system)
- of remaining 850K
. very little will have been spent by late fall
. some fraction can be cancelled/never spent
BUT
. some fraction is irrecoverably lost because of schedule slip (we're stuck with schedule slip... this is OK)...  This fraction (up to 500K) will be determined by the new contract negotiated (& the loopholes/program developed)
=> briefed this to George; he'll set up meeting