9-17 ACCEPTANCE TESTS

(Jim Betts, Chuck Guteis, Tom Jenkins)

Acceptance tests are done at subsystem levels and at an integrated level (all in early December)
Jenkins is writing 1st cut at ATP now.....
submits it to NASA >45 days before the 
acceptance tests start

They would like to incorporate mission time-line
tests as part of acceptance tests
- This is a good step as long as:
1. "engineering" tests are performed
2. "display verif"-type runs are performed
(shows that things that [[underlined]] aren't [[/underlined]]supposed to work, don't)
3. malfunction runs are included

Our input:
[[written in red]] Ron   1. malfunction runs on sim/ac OV ... conelate to their malfs, choose good runs to use