This transcription has been completed. Contact us with corrections.
9/5/79 PDRS STAFF MTG weekly staff meeting (held by Bostick & McCullough). Items: 1. Bostick & MucCullough going to KSC to discuss -baseline RMS, and SPAR's responsibilities/interfaces at KSC - STS-1 & implications for KSC if RMS flies 2. PGHM meeting (Payload Ground Handling Mechanism) scheduled for 9/18 @ KSC 3. 2 PDRS items will slip into monthly directorate review on 9/18: -coefficient of friction problem - C455 in latches 4. Kraft, Cohen, & Thompson are going to SPAR 9/19 5. NRCC is announcing schedule slip: 20% chance of 3/5 RMS delivery 50 % chance of 4/29 they'll be publishing proposed schedule,