9/5/79  PDRS STAFF MTG

weekly staff meeting (held by Bostick & McCullough). 

Items:

1. Bostick & MucCullough going to KSC to discuss
-baseline RMS, and SPAR's responsibilities/interfaces at KSC
- STS-1 & implications for KSC if RMS flies

2. PGHM meeting (Payload Ground Handling Mechanism) scheduled for 9/18 @ KSC

3. 2 PDRS items will slip into monthly directorate review on 9/18:
-coefficient of friction problem
- C455 in latches

4. Kraft, Cohen, & Thompson are going to SPAR 9/19

5. NRCC is announcing schedule slip:
20% chance of 3/5 RMS delivery
50 % chance of 4/29
they'll be publishing proposed schedule,