5. Engineering model RMS is going to RI for the MPM systems test
6. Working groups meeting may move to JSC - 26th or 27th (Sept)
7. telecon to discuss validation runs 9/12 at 1430
8. telecon to discuss "allowable levels of acceleration" (impacted to RMS orbiter) 9/20.
9. PEP: RFP prepared by October, expect bids in by ~ December, chose [[choose]] by early summer, start building 10/80. RMS mods are required (info from JR)