25 NOV81 - Flight Planning mtg (Y, Cr, E, T, L, F, Kranz) (1) try to relieve PDP timeline by eliminating some procedures & delaying some to CAP: • delete 1st IMU align (no longer req. for "Go for ORBIT") make evening CAP alignment 1st of crew day • make 1st mnvr on the PRCS (rather than wait for VRCS to warm up) • delete COAS Cal … it worked (with ~ same bias) on STS-1 & -2. • delete FC purge - remove it from go/no go, & make evening FC purge the 1st of crew day • no need to cycle the doors ---------- • launch with the teleprinter hooked up & audio panels in teleprinter configuration • delete most of mid-deck "unstowing" bubble … unstow minimal # of things • perform PL activation from the ground (to the extent possible) • stow theodolite upstairs? (2) desired changes to the CAP • add 15 min in morning & afternoon of each day for each crewman, for "housekeeping."
Transcription Notes:
kranz should be krang