[left margin]]RMS (OMI)[[/left margin]]
[[left margin]]5/1[[/left margin]] OMI Review (KSC - Edwards, VanHoosen, Aikenhead, Young,...)
Review of V1110 (currently scheduled ~ end of June).
Includes: RMS checkout pre-mechanical mate, CCTV checkout, mechanical mate.  Proposed re-ordering:
01 - pre-ops set-up (support)
02 - pre-ops set-up (orbiter)
03 - TPS ops set-up
04 - call to station
05 - RMS sys init. [omit BTV [[may be BTU?]] check - it's in 1082]
06 - RMS brakes
09 - RMS direct drive
10 - RMS EE
11 - RMS single jnt/curr limit
[[right margin]]test curr lim during capture in MAN AVG mode, with EE MODE = AUTO (current limits on all jnts at once)/right margin]]
07 - AUTO SAFE/BRAKE VERIF (needs work. Telcon between P.K. & Peter C.)
12 - RMS TEST MODE (make sure this is before CURR lim check & HC check)
13 - RMS MANUAL AVG mode
14 - RMS AUTO MODE
15 - RMS OPR CMD MODE
16 - RMS B/U (add clean-up in primary)
18 - SPEE I/F & SHLDR BRACE relatch
19 - RMS DFI (can be done in parallel with any test)
08 - HTR BUS VERIF
17 - RMS CCTV
20 - RMS/ORB mechanical mate
21 - RMS FLOOD/MATE
22 - MPM functional checks (w/TPS on)
23 - arm/PLBD envelop check [[swapping arrow]]
24 - RMS CCTV check-out [[swapping arrow]]
25 - snare cable check