integration review (STS-2) notes: (1) PLB flood sits right under OSTA (2) changing out freon types (3) hi-power S-band doesn’t work with SIR-A 6/22 OMI schedule: 1110 up in the air [[margin]]mtgs[[/margin]] Pwrdn mtg this p.m. CEIT still 6/28 (Sat midnight for 1 shift) ATO dump CR approved MPM/MRL testing at RI: μswitch problem with MPM’s may be a rigging problem. [[left margin]] MPM [[/left margin]] They were set 2 months ago & worked well... 2 months later they were offset. Need to check with RI/KSC people: how do we verify these after installation? Thermal (hot case) testing this week at RI 6/23 On-orbit sim (load checkout - continuous comm) used some STS-2 books, including xeroxed PDP - started sim at OMS 2 + 1 minute [took comm after PLBD ops] (1) DSC failure (OF 3) - an instrumentation failure, which gave appearance of CNTL BUS problem, H2O TK problems, etc. REF DATA book gives synopsis of failed indications (2) R18.11 DAP is coded wrong: a negative pitch [[strikethrough]] [[?]] [[/strikethrough]] cmd