(7) 1110 schedule: [PWRDN on SUNDAY]
Latch tb & heater measurements re-wiring require breaking connection & ∴ retest of MPM/MRL. Mechanical mate probably early 2nd shift Friday

(8) IPR on latch/rel/RDY indications

(9) RHC mount (coming in ~7/3)

(10) qual EE

(11) RMC coord logs 

6/29
• CEIT complete PL rcdr changeout not reasonable, DFI rcdr changeout is reasonable. (2nd half on 13th & 14th)
Wireless comm to be used in OIT. Nominal config: HIU + star headset until theodelite deploying...then go to wireless

• 4400# deficit for ascent. Solution: 1) seasonal update - 800#, 2) decrease loft by 50% - 700#, 3) 38° inclination - 1600#, 4) 130 x 130 orbit - 2300# => +[[plus]] 5400# gained (1000# over)

• 41C deorbit program to be used in long sim

• PLB lights - mod kit installed....total of 7 (6 in bay, 1 bulkhead) 1) 3 failed on STS-1, all from same box (KSC test showed failure), 2) new lights can't be used with OSTA (heats pallet)

5 ft candles @ [[at]] 15' per light (would show PL @  ~750')