24 AUG - MDAC (HUNTINGTON BEACH)
ISOL/PCM PWR: power to SCU (& therefore required for SCA Enable) and to the cradles' PCM
SCA ENABLE: provide 2PV from the SCU to the transmitter on the SCA
note: SCA ENABLE determines which SCA is controlling the sequence. PL 1 or 2 determines which SCA is providing feedback data. In principle, could be controlling on one, but using data from the other... 
MDAC didn't want that, so they added logic to their SW to prevent that

LIM OVERRIDE - on CONTROL spec...removes check during terminal sequence that shuts down seq. for +-10% [[triangle]] on spin rate.  Plan is to set FDA limits at the space crafts go/no go criteria

POST-DEPLOY AUTOMATIC SEQUENCE:
1. spin table stops (using brakes)
2. there's no indexing of the table - its' allowed to stop anywhere
3. the restraints stay "OUT" (not Engaged)
NOTE: table will despin without brakes...it just takes longer