23 JAN
KSC testing (SPARX)
• check on what SPARX will go through in VPF. ("CITE" - where all cmds can be sent? If not, can we rig up rf link and hanger S and use GPC software to cmd SPAS/MAMS)
• ensure that OPF testing includes all cmds (equivalent of pad testing on STS-7)

41G contact: NEIL GRIFFITH/FRANK NEWMAN } VITT

PENNINGTON/SORENSON
• estimate flt tech start ~ 2-3 wks after STS-11
• before that ... work on ATO problems/priorities

27 JAN
• FLT TECH scheduled for 24 FEB (moon/382)
• KSC test conductor for STS-17: TOM ST. ONGE FTS 823-3623 (2958) (info from Bill Spradlin)