- Several should be installed to wall and ceiling areas as well as to the floor. 

-Use of the seat mounting holes could be used for foot restraints.

-It was agreed that CB/S. Ride should be consulted on this entire subject.

WASTE COMPARTMENT
-The WCS locker was packed so tight that it bulged. The locker was too full - too loaded. Fiberglass bulged. [[16c will look @ this pers hyg boxes?]] 
-Yellow velcro was added on the port side of the WCS. Velcro should be permanently located where the yellow is. [[in work]]

SHUTTLE PERSONAL OPERATIONS COMPUTER (SPOC).
Deployed by L10 panel. Used very much; left up until deorbit burn; got hot but worked fine.

WINDOW WASH KIT
Very good item. Used a lot.[[stow 2 for dual shift ops (in camera bag)]]

MULTI-USE MOUNTING BRACKETS
The "Bagens" were OK, but the bracket-to-camera and the bracket-to-Orbiter interfaces were not tight. This caused problems. Brackets-to-quick shoe mounts were not tight. The crew requested that a means for tighter set ups be provided.[[Photo group aware + working on it (new prototype?)]

FOOD SYSTEM AND RELATED
-The crew provided a 35mm photo which showed the clutter.
-Both of the food warmers were used. The "Y" cable worked. There was never an overload trip.
-However, the crew really needed another hot water system. It was very inconvenient using cold water for washing. (test port 4)? [[Investigate to see about hook [guess]]]

Transcription Notes: