35 • Malf procedures (all work on them) lost (out with the trash) • SES: decision due in 2 weeks on PDRS portion of on-orbit sim (& on-orbit ops in general) Staff mtg •agenda for malf w.g., & segment of 45 report passed out •Tues afternoon 1/720 GPC malfs (Austin?) • JWB on overlay--will come back next week with hack at MDF schedule • Ball Bros: suggest looking at lightweight latches (PA agrees) [deliver >1983, if begin study now] • D&C qual & flight panels failed in vibration testing (T.C. Wilson took Clive A's place with SPAR/CAE) • FMEA on orbiter jettison system? [[left margin]] R RICHARD [[/left margin]] • Yardley letter: STS-1 R16 STS-2 R18 R19 "not being pursued in DDT&E" • "-3" MIA's: when powered down, they emit a "glitch" that could effect other units....but -4's don't exist anywhere • KSW SW patch not yet run on Simfac -Send MPAD the RPAT notes