Working Group
- IECM w/ PRCS action item. In auto mode, from
point to point with orbiter in Vernier, PRCS on & DAP
in pulse.... check that no firings are in singularities.
PRCS off for other IECM (monitoring) sequence.
- SES - prox ops in by ~ mid-August
RMS TBD
- NRCC will submit FUR for real-time photogrametry
tests in the MDF
- RMS lights are incandenscent (docking light also)
& can be turned off & on. PL bay flood lights
can't - they have to be left on for ~15 minutes.
- STS-3 FTO's (going through the Ehlers/Ride 4/9/80 memo)
1) GF #2 & #5 only
all tests with #2 (but not dynamics part of -6 & -8 i.e. not common validation runs)
deploy & berth w/ #4
dynamics w/ #5 (352-10) {(352-6) (352-8)}don't need to do single safing & braking with #2
2) #288 issue B will be out 7/14
& will have PRCS tables & comments
3) Singularity management need not be clicked,
but PRCS firings "near" singularities will be kept
4) "loaded position hold" test should be put back in
5) DAC recommendations & procedures are in from NRCC