SMM - (Don Murray - Goddard; Wayne Eaton - JSC)
1300 MONDAY - SMM test plan review
1 week in 1-g mock-up (1st cut at markings, etc)
1 week in MDF (starting 7/28) [Kerwin, Kelso, Ride]
3-point berthing, pivot structure. Basic structure can be placed in different locations in the bay - different in -x^ and also in -z^. MDF testing will check both "high" & "low" positions, & one position forward & one aft (farthest extremes).
check: (1) visibility with objects in the bay (both positions)
(2) camera failures
(3) markings required (common set?)
(4) can ready-to-latch be detected visually? (there are no R-T-L sensors now)
(5) are guides required? (3-point concept.... what are the cues?)
(6) keel camera?
(7) perform a night run, with flight cameras