13 Feb (KSC - Commission mtg) KOHRS - ~2000 pieces of paper opened pre-launch 51L (so far) L-1 MMT: (1) 7" rain vs 2.5" rain ""nom." Concern = wt of H20 in the tile (no other concerns expressed.) What were other high cases of rain. ICE team 85% of same people since STS-1 "freezer plan" exists since 51C (concern is for facility ice, &/or facility pipes. ICE team: 28 Jan 0700 (IR readings) • Only launch commit criteria on low T = 31° F ambient • Lift off loads reconstruction ~1 wk away • MSFC "very interested" in L/O loads ([[?]] heard rumors on high L/0 loads) • RH SRB aft joint/seq found by sonar