Viewing page 78 of 138

This transcription has been completed. Contact us with corrections.

[training Eng to work real-time environment

[Following notes are contained within one set of brackets]

- How often: comm w/ HQ (now)
- "Work-to" Schedule?
Mtgs characterizing work done to RTF?
Schedule JSC -> HQ

Characterize 107 in [[strikeout]] the [[/strikeout]] flow (relative to ISS Fits [[best guess]])
(Schedule relief) 
Curry

Who's job is it to see that integrated risks are developed?  Originally (STB-7) FA for foam assigned to orbiter

Orbiter RTF   Ron's contempant [[best guess]] Parker counts MSFC [[best guess]]
- HQ decision ISS had priority
The priority review memos/margin w/ HQ
Okesfe/Holloway development disease
Sustainability = Safety (not different things)