Viewing page 80 of 279

This transcription has been completed. Contact us with corrections.

the 15th of November, 61 days from the time of entering into this agreement up to the 16th of Feb we have 154 days this gives us 93 days on the work more than was required by the second contract. The time charged in my Bill was 79 days. I do not recollect how it was that I did not charge the 93 days, but as it is, we have 15 days which may be charged, to other causes, than that of delays from not having materials.