11

30 Nov 

TITLE ________________________
Project No.__________
Book No._______ 
  
From Page No. _____

ASTRO MTG 

SAIL: IUS integ on STS
FSL: Orbit (202) staff starts 14 Dec
SMS: 1st 302 LOAD UP TODAY OR TOMORROW - BOTH BASES
No IBM load brief: J.O.
& CG giving [[shape, triangle]] brief WED 1400]]

Williams: STS-3 turnaround flow brief
Due out off 5 Dec 10 Wks
VAB 2 Wks 2/19 R/O
Pad 4 wks 3/19 earliest launch

John Y: STS÷3 L,F/Ma,H
Add 2 1/2 WRS RMS (9 1/2 HRS on day 3)
3 PDP edploys, 2 IECM deploys

(Possible January vary start of constrained motion test)
May go to 2 GPC's 0/0
Star trkr autonomous nav test; trcan nav test
Flt planning time specifically for housekeeping & teleprinter

STA's down: 1 for 2 wks; 1 til jan,

Ed Rainey & Michelle Brekke's SMS' teams dedicated to STS-3

To Page No._____