Tim Short (RI) OSS-1 cockpit installation

Rafael Garcia called back Theodolite
was in 1-6 tonr with Fred G & EI.
Concerned that .002- .005 repeatability wouldnt hold in O-g, When only 17 lb spring preload is effective (no unit weight helping)
K & E to try counterbalance test to sim O-g.
Onizuka concerned about stability
wants bearing tolerances reduced
wants verifich unit could withstand inadvertent use as handhold
Bl 13 still holds position that braces of .002- .005 can be removed in analysis.

Flt computer not going to fly STS-3 (maybe never)

No vibration anal. ever run on fly config.

El told Garcia to have concrete data & decision by 9 Jan. 
Hope to shoot door targets 1/24 with CEIT

To Page No. __________

Witnessed & Understood by me, __________________________
Date ___________
Invented by _____________
Recorded By ____________
Date ___________

Transcription Notes:
---------- Reopened for Editing 2023-03-29 16:37:00 ---------- Reopened for Editing 2023-03-29 19:20:50 ---------- Reopened for Editing 2023-03-29 18:45:43 ---------- Reopened for Editing 2023-03-30 11:10:03