Project No.__ TITLE 1/8/82 Book No.__ 39 From Page No._ Charlie Floyd - Latest STS-5,6 flows out. Some S/W & test sked concerns Flt cnte E-T-E sked 7/26 10 days after pwr up in OPF (was originally a factory test...; patch developmt concern STS-6 1st 3/W delivery = 27 days after OPF arrival. IECM functionals commenced ~ noon; finished ~ 2000. PR on high resistance between REM & IECM; planned to go for waiver or clean bolts (paint) if waiver not approved. 1/10/82 Phoned for OSS-1 update: P/L in & elect/cooling hookups in work @ 1300. To Page No.___ Witnessed & Understood by me,_____ Date_____ Invented by_____ Recorded by_____ Date_____