Project No.
TITLE 3/15/82 Book No. 67
From Page No.

PMD All elerons on; BF on. 
MPS P checking almost cplt
APU plumbing installed; c/o IW with cryo sets 
No nav base - no IMU, AA ect testing. Done next month
PBD saga getting a bit well - stbd door now open. 

KSC Ordnance installn starts today.
S0007 preps Wed, count starts Thurs. 

DPS SPARES AT KSC  as of 3/12/82 - Ed McKenzie  

GPC's CPU S/N 24 from FSL
10P S/N 22 - " -

DU S/N 13 (CRT4) new out of Owego

DEU S/N 20  used in KSC DPS lab "recently" 

Keybd S/N 11 in storage "a long time"

MMU  none  S/N 10 installed 3/9/82
S/N 13 to be shipped form OV-099

MDM  FF S/N 61  at KSC - 1 yr, unused
FA S/N 43 never pwrd on since KSC arrival (when?)  
LA } none
LF
PL S/N 75 ?

No bench-level maintenance (card swaps) at KSC  

MMU failure causes - motor-brush noise (bad seat on commutator - affects new LRU's)
oxide particles; motor brush mat'l wear buildup
tape slippage due capstan wear
To Page No.
[[6 Columned Table]]
| Witnessed and Understood by me, | Date | Invented by | Recorded by | Date |   |
|---|---|---|---|---|---|